The treated plate has been bolted down to the foundation wall and the post and beams have been installed. The rim joists are placed on the perimeter of the building and the floor joists are measured and layed out for installation.
The subfloor is 3/4" T&G and is nailed to the floor joists after apply construction adhesive to the top flange of the joists.
With the subfloor now in place the exterior walls are ready to be built. The bottom and top plates are measured and cut and are marked for window and door placement. The studs are marked at 16" on center and the studs, cripples and headers are all nailed into place. Sheathing is applied to the exterior side, and the wall is ready to stand.