Clean & Backfilled

Now that the foundation walls have been poured and the forms stripped away we can begin to clean up.


























With the forms stripped, the foundation walls can now be waterproofed.


























It is always good to get the foundation cleaned up and backfilled. We now have a good level site on which to construct the home.


























































We will be moving into the framing stage later this week, after a few more days of allowing the concrete to cure. Framing is an exciting phase of the construction as every day you can see progress. That cannot be said about all the phases of the project. Some seem to drag on forever, with little progress, but each day a little bit more gets done. With framing you begin to see the house take shape. You can envision each room as it goes up. Think about how you're going to use it and furnish it. That is real meat & potatoes stuff.



We will have the lumber delivered sometime today for the floor package. That is the treated plate with sill seal to go onto the foundation wall. The treated 4x4 posts and the 4x10 DF beams that will hold the floor. The TJI engineered floor joists that make up the floor platform and the 3/4" OSB T&G that is the subfloor membrane. All of that should be done by the middle of next week and then come the walls.




Along the way, in the coming weeks, we'll be ordering the window and door package and before you know it, the sum of the parts will begin to resemble a finished product.